Right now it is at least a three step process with three different screens to make a CO:
1. Total up CO on the Change Order Tab within the Estimate
2. Leave that screen and make a CMR on a new screen and put a status if not immediately approved
3. If the CO is then approved, Go back into CMR and list as approved, THEN...
4. Make it a Change Order and go into the Change Order screen to make it part of the project.
This process is so inefficient. We should be able to total up the proposed CO and set the status from one screen. Then if it is approved, change the status on that screen to approved and it immediately takes you to the CO screen where you approve and execute it into the project.
Dear Viewpoint Suggestion Box contributor;
We at Viewpoint sincerely thank you for your contribution to Suggestion Box on how we can improve Viewpoint products. While we can’t do everything at once, we rely upon your feedback to help guide the prioritization of our product improvements, and Suggestion Box is a critical tool for us to understand and prioritize our customers’ needs.
Viewpoint reviews Suggestion Box regularly for all of our products and updates statuses, adds comments, and performs various house-keeping (including deleting) as needed to ensure that Suggestion Box is maintained as a productive environment for product enhancements requests.
© 2023 Trimble Inc. All Rights Reserved. Viewpoint®, Vista™, Spectrum®, ProContractor™, Jobpac Connect™, Viewpoint Team™, Viewpoint Analytics™, Viewpoint Field View™, Viewpoint Estimating™, Viewpoint For Projects™, Viewpoint HR Management™, Viewpoint Field Management™, Viewpoint Financial Controls™, Vista Field Service™, Spectrum Service Tech™, ViewpointOne™, ProjectSight® and Trimble Construction One™ are trademarks or registered trademarks of Trimble Inc. or its affiliates in the United States and other countries. Other names and brands may be claimed as the property of others.
This whole CO/ CMR/ Approve/ Owner CO process is a huge waste of time, you literally have to touch it 5 times. NOT TO MENTION the fact that the verbiage doesn't carry over from the Estimate even in the descriptions!! it shouldn't be this complicated. a PM should be able to write a COR/CMR get it approved and it automatically goes to the AIA / Accounting for Billings
There is so much time wasted on issues like this with the software. It's not just the change orders think about lean notices when you do the project set up. You put the information there and then you have to go into the lean management and put the start date the lien noted state and everything like that again. The main problem is is once you're up and running you're so invested in this software that its hard to make the decision to move to a different one
yes please,
This is nearly two years old and says it is Likely. Any updates?
YES, YES YES!
Got my vote
Thanks Cindy. Wish I could spread the word to get more to upvote!!
I would love to press the vote button 100 times. It's time consuming and trying to amend change orders takes way too much time.